Personally,
DV focus on the test and inspect on the single product that newly developed(For Carryover Parts, DV is not necissary).
generally, it's implemented by a soft tooling in this field, whose cost is almost the same as a PV tooling.
PV focus on the test production line in which your new product is gonna lanuch, which is supposed to be based on condiontions (Production tooling, equipment, operator, material, process, and enviormental)that is just for the volume production, which is for PPAP Approval and Pilot Production.
Basically, it's widely used in famous OEMs and its Suppliers. yet for some National OEM, PV and DV are combined together..
Wish you could see the above explanation. sorry my PC doesn't support Chinese input today, if you have any questions. just feel free to conact me on:michael3626@gmail.com.
looking forward to hearing from you sooon. happy to be your friend btw.